Skip to main content
Hydraulic Studies and Development of the Water Supply System

Hydraulic Studies and Development of the Water Supply System

Inquiry

Project at a glance

Radian worked with ILF on hydraulic studies to assess and develop Jubail Industrial City’s water supply, including reinforcement through Marafiq’s desalinated-water pipelines.

Diameter of the main transmission line studied
About1,500mm

Radian’s scope of work

  1. Assess water sources and analyse present and future demand
  2. Model the network and analyse flow, pressure and bottlenecks
  3. Identify the transmission route and connections and assess the pumping station
  4. Study surge protection and prepare maintenance plans and tender documents
  5. Build and update the WaterGEMS hydraulic model and analyse operating scenarios
  6. Assess Marafiq’s Northwest Pumping Station (NWPS) and identify hydraulic, mechanical and electrical modifications
  7. Compare technical and financial alternatives and prepare CAPEX estimates and an operations and maintenance plan